Bi-Monthly Updates
 
September:
  • Structual Design Team:
    • 9/14/14: Began External Load Calculations
  • Foundation Design Team:
    • 9/24/14: Advanced Drilling & Co., came on to Site Location to perform Geo-Technical Boring
October:
  • Structual Design Team:
    • Finished External Loads and began Visual Analysis Model
    • Calculated Tributary Area Spacing for 20ft Spacing
  • Foundation Design Team:
    • Performed Soil Identification Testing (i.e. Sieve Analysis and Moisture Content)
November:
  • Structual Design Team:
    • ​11/12/14:Determined Tributary Area of 15' and selected W36x135 Member
    • Finished Earthquake Load Calculation, and Completly Updated Visual Analysis Model
  • Foundation Design Team:
    • 11/1/14: ​Finished Soil Profile 
    • 11/13/14: Completed Sieve Analysis
December:
  • Structual Design Team:
    • ​12/15/14: Reading Direct Analysis Method
​​February:
  • Structual Design Team:
    • ​2/19/15: Trial I of Building Opitmization in Visual Analysis 
  • Foundation Design Team:
    • 2/19/15: ​Began Bearing Capacity Equations
​​​​March:
  • Structual Design Team:
    • ​3/27/15: Finally Optimized Portal Frame with and without Tapering
    • 3/28/15: Began Stringer Design 
    • 3/28/15: Bearing Plate Design (For Foundation Connection) 
    • 3/29/15 Start Google-Skecth Up Model
  • Foundation Design Team:
    • 3/29/15: Finised Foundation Design (Adjusted Results based on Tapering)
    • 3/29/15: Began Parking Lot Analysis
​​​​April:
  • Structual Design Team:
    • 4​/22/15: Finished Connection Design
    • 4/28/15: FInished Cost Estimate for Structurual Team
  • Foundation Design Team:
    • 4/19/15: Added Reinforcement to Foundation Slab
    • 4/22/15: Finished Cost Estimate for Foundation Team
​​May:
  • Structual & Geotechnical Design Team:
    • Finished Senior Project Presentation
    • Finished Senior Project Report
    • Finished SENIOR YEAR!
 